- Home
- About the company
- News
- Construction of the "Gruzopodyom" Logistics Center
Construction of the "Gruzopodyom" Logistics Center
16 октября 2024We are sharing the progress on one of our key internal projects of 2024 – the construction of a logistics center. To date, the following works have been completed: industrial floors have been poured across the entire area of the future complex, engineering communications have been laid, and the construction of the administrative and utility building is ongoing.
Let us remind you that the decision to build this facility was made to optimize production processes, increase the efficiency of the enterprise, and improve the plant's infrastructure. The future logistics complex will consist of three main sections:
- Heated warehouse (1500 sq. m) with 2600 euro-pallet spaces for temperature-controlled products.
- Cold warehouse (900 sq. m) for products that do not require heating.
- Finished goods warehouse (2000 sq. m).
Subscribe to news